Which Permit You Need, and When

December 6, 2023 · 4 min read · Reviewed September 2026

Applies to Renovations and additions across Canada. Permit names, thresholds and which trades need separate applications are all set locally.

Building permit placard posted in the window of a house under renovation

People ask whether they need a renovation permit or a building permit as though they are different documents. In most of the country there is one building permit, and what varies is the application stream, the drawings required and the fee.

The more useful question is what the work touches. Structure, egress, fire separation and the systems in the walls are what trigger review, and they trigger it regardless of whether you call the project a renovation, an alteration or a repair.

That framing also explains the exemptions. Painting, flooring and cabinetry change nothing a reviewer cares about, so they need nothing. The moment a wall moves or a circuit is extended, something in scope has changed.

The second useful question is how many permits. A single renovation can need a building permit plus electrical plus plumbing plus gas, issued by two or three different bodies with their own inspectors and timelines.

What triggers which permit#

WorkBuilding permitOther permits likely
Paint, flooring, trimNoNone
New cabinets in placeUsually noElectrical if circuits change
Moving or removing a wallYesElectrical if wiring moves
New or enlarged openingYesNone, unless services are in the wall
Finishing a basementYesElectrical, often plumbing
Adding a bathroomYesPlumbing, electrical, sometimes ventilation
Deck over a height thresholdYesNone
Furnace or water heater swapUsually noGas, sometimes electrical
Re-roofing like for likeOften noNone
Adding a suiteYesElectrical, plumbing, sometimes gas

The row people misjudge most is the wall. Non-structural walls still often need a permit because removing one changes egress, room dimensions or the path of services, and because whether a wall is load-bearing is not always obvious from below.

Mechanical swaps are the other one. Replacing a furnace or a water heater with an equivalent unit frequently needs no building permit and does need a gas permit and an inspection, which people discover when they try to sell or when an insurer asks.

Why the streams differ#

A small interior alteration and a two-storey addition are both building permits, and they are not reviewed the same way. Departments run streams so simple work does not sit behind complex work in one queue.

The differences show up in what you have to submit. A simple stream may accept a sketch with dimensions. A full stream expects a complete drawing set, structural design, energy compliance and sometimes a designer’s qualification number. Fees follow the same split.

Some municipalities also run fast-track or over-the-counter processes for defined work such as decks, furnaces or basement finishing. If your project fits one, using it is much quicker than the general stream.

Ask which stream your project lands in before preparing drawings. A full set for work that qualified for a simple stream wastes money, and a sketch submitted into the full stream wastes weeks.

Sequencing several permits#

  1. List every permit the job needs

    Building, electrical, plumbing, gas, and anything municipal such as a road occupancy or a demolition permit. Do this before booking trades.

  2. Find out who issues each one

    In several provinces electrical goes to a separate authority. Gas is frequently separate again. They do not talk to each other about your schedule.

  3. Confirm who pulls which permit

    Trades usually pull their own, and the building permit is normally the owner’s or the general contractor’s. Assuming somebody else did it is a common way to stall a job.

  4. Sequence the inspections as well as the permits

    Rough-in inspections have to happen before insulation and drywall, and different inspectors may need separate visits. Build that into the schedule rather than discovering it.

  5. Close every permit at the end

    Each one needs its own final inspection. An open electrical permit is as much of a problem at sale as an open building permit.

Common questions#

Is there such a thing as a renovation permit?
Some municipalities use the term for a stream of building permit. It is a label on an application type rather than a separate instrument.
My contractor says none is needed. Should I check?
Yes, with the municipality. It is a free call, and the consequences of unpermitted work land on the property and its owner rather than on the contractor.
Does a permit expire?
Usually. Permits commonly lapse if work does not start within a period or stalls for too long. Extensions are normally available if you ask before it expires.
Do I need one to replace a window in the same opening?
Often not, though it varies, and enlarging the opening changes the answer. Bedroom windows raise egress even for a same-size replacement.
What about work in a condominium?
You may need the corporation’s approval as well as a municipal permit, and the declaration will say what can be altered. Both processes are separate and both can refuse.
Can I pull my own permit as a homeowner?
In most places yes, for work on your own home, and you take on the responsibilities that come with it. Some trades work is restricted to licensed contractors regardless.

Looking for the number?

These pages state the requirement and name the document it comes from.

Ask your own code question

Canadian Codes answers questions like this one from national, provincial, territorial, and municipal sources, and cites the document, section, and page so you can check it yourself.

Try it free →