What a Plumbing Rough-In Inspection Checks

September 12, 2024 · 4 min read · Reviewed September 2026

Applies to Plumbing work in Canada under the plumbing code as adopted provincially. Permits and inspections are usually municipal, and in some provinces separate from the building permit.

Plumbing rough-in with drain lines, vent stack and capped stub-outs in an open stud wall

Plumbing has two halves and only one of them is intuitive. Supply piping is under pressure, so a leak announces itself immediately. Drainage runs on gravity and air, and when it is wrong the symptom is a smell, a gurgle, or a trap that empties itself months later.

That is why the rough-in inspection exists and why it concentrates on drainage, waste and venting. It happens while everything is visible, and after that the system is behind finishes for the life of the building.

The single concept behind most of it: every trap needs a vent, because a trap holds water and water is what keeps sewer gas out of the house. Drain a fixture without adequate venting and the flow siphons the trap dry.

What gets checked#

ItemWhat the inspector looks forWhy it matters
Slope on drain linesA consistent fall within the permitted rangeToo flat and solids sit; too steep and water outruns them
VentingEvery trap vented, vents sized and connected correctlyPrevents traps siphoning and holding sewer gas back
Trap arm lengthDistance from trap to vent within limitsToo long and the vent stops protecting the trap
Pipe supportHangers at required spacing, no saggingA sag becomes a low spot that holds waste
FittingsCorrect fittings for direction of flowSanitary fittings on drainage, not tight elbows
Materials and jointsApproved materials, correctly solvent-welded or joinedMixed or improper joints leak later
Test in placeWater or air test holding for the required periodThe only direct proof the joints are sound
ProtectionPlates where pipe passes close to framing facesA screw through a drain line is discovered slowly
CleanoutsPresent and accessible where requiredYou will need them, and not behind drywall

Slope catches people because both directions are wrong. Too flat and the water leaves solids behind. Too steep and the water runs away faster than the solids move, with the same result. The permitted range exists for that reason rather than as a minimum to exceed.

The test#

The system is tested with the piping exposed, usually by filling the drainage with water to a required head or by pressurising it with air, and holding it for a set period while the inspector watches the gauge or the level.

Set the test up before the inspector arrives rather than while they wait. A system that has been holding for an hour is a better demonstration than one being filled at the moment of inspection, and it also gives you the chance to find your own leak first.

Freezing is the seasonal complication. A water test in an unheated building in winter is a poor idea, and air testing is the usual alternative. Agree the method with the inspector in advance.

Under-slab drainage gets its own moment. Anything below a basement slab has to be tested and inspected before the concrete goes down, and that inspection is separate from the one for the piping in the walls above. Missing it means breaking concrete rather than opening drywall.

  1. Plan venting with the framing, not after it

    Vent routes need paths through the structure. Deciding them once the joists are in and the ducts are run is what produces non-compliant layouts.

  2. Set out fixtures precisely

    Stub-outs are set from finished wall and floor surfaces. Roughing to framing dimensions leaves everything slightly out once the finishes go on.

  3. Protect the pipe from fasteners

    Plates where pipe runs close to a stud or joist face, exactly as for electrical cable.

  4. Set the test early

    Fill or pressurise well before the appointment so you find your own leaks and the inspector sees a stable system.

  5. Coordinate with the other rough-ins

    Plumbing, electrical and mechanical share the same cavities. Whoever goes last inherits the problem, and drainage has the least flexibility of the three.

Common questions#

Can I do my own plumbing?
In many provinces a homeowner may work on their own home under a permit, with inspections. Some work and some materials are restricted to licensed trades. Check locally, because it varies.
What is an air admittance valve?
A one-way valve that lets air into the drainage system without a vent running to the roof. Acceptance varies by jurisdiction and by where it is used, so confirm before relying on one.
Why does my drain gurgle?
Usually a venting problem. The system is pulling air through the trap because it cannot get it from a vent, and that is the same mechanism that eventually empties the trap.
Does the supply piping get inspected too?
Yes, generally at the same visit and with its own pressure test. Drainage and venting are where most of the review time goes.
What if I have to cover it before the inspection?
Talk to the inspector first. Covering work before it is inspected can mean uncovering it, and the cost of that falls on you.
Do I need a cleanout for every fixture?
Not every fixture, and there are requirements for where cleanouts must be and that they stay accessible. Building one into a finished wall defeats its purpose.

Looking for the number?

These pages state the requirement and name the document it comes from.

Ask your own code question

Canadian Codes answers questions like this one from national, provincial, territorial, and municipal sources, and cites the document, section, and page so you can check it yourself.

Try it free →